Italy: biomethane, construction begins! CIB Service reminds us of the requirements to gain access to incentives
For all future producers of biomethane, which following the tenders are now starting the construction phase of their plants, it is important to remember a series of mandatory requirements to receive the incentive. CIB Service reminds us that:
- The start of work must be communicated to the energy services operator (GSE) within 30 days of the start of work date;
- The hypothetical date of entry into operation of the plant must be communicated to the GSE between 120 and 60 days before the same date;
- The effective date of entry into service must then be communicated within 30 days of that date, also uploading a series of documents for the reporting request.
Find out more in this interview or by contacting CIB Service directly!